Global data center electricity consumption is set to double by 2030, driven by artificial intelligence infrastructure expansion, according to the International Energy Agency.

The IEA forecasts data centers could consume approximately 1,000 terawatt-hours of electricity annually by decade's end. In Texas, Virginia, Finland, and the U.K. the combined capacity of data centers awaiting grid connection already exceeds current peak electricity demand—a hard bottleneck on new facility deployment.

The constraint is structural. Tight supply chains, local opposition, and limited grid capacity are restricting data center build-outs. Without significant power grid upgrades, connection wait times will lengthen and grids will face forced curtailment when demand exceeds supply.

Meeting projected 2035 demand requires 26 million kilometers of new transmission lines and replacement or refurbishment of 16 million kilometers of existing lines. The IEA notes critical material supplies—cop cables, transformers—are already constrained.

Under current policies, grid spending is projected to increase 75 percent over the next decade. The agency identifies power networks as one of the largest energy investment opportunities ahead.

IEA Executive Director Fatih Birol said, "The pressures of the current crisis must not obscure the choices that will shape energy security, sustainability and prosperity for the decades to come."